Brockley Week 25


There has been good progress since our last update.

Internally the timber panelled ceiling has been taking shape this week and really transforms the space having been staring at a vapour control membrane for the past few months. The floor boards are also ready for installation and will be in before Christmas. The kitchen carcasses and bespoke modifications have also been worked on and are in place so that we could get the quartz worktops templated but the joinery on the doors and drawer fronts will have to wait until after Christmas.

Externally the charred timber cladding has arrived, but being a bit hampered by the weather of late this has again been pushed back until after Christmas.